Value Delivered
As the prime contractor, Dynalectric Company (Colorado) delivered a complete emergency power supply system infrastructure upgrade at Rose Medical Center. We also installed associated high- and low-voltage systems, and performed mechanical and general construction.
To help ensure zero disruption to the facility’s daily and emergency operations, we coordinated the project schedule to a high level of detail.
Client Objectives
Rose Medical Center required emergency power infrastructure upgrades.
Solutions
Dynalectric Colorado provided and installed the following electrical upgrades at six different areas of the facility:
- Switchboards and panelboards
- Automatic transfer switches
- Motor control center units
- Chiller substation
- Digital power metering system
- Substation and generator disconnects
- As-needed temporary power